Private Insurance ClaimThis project involved rectification works following a landslide that impacted property. We initiated the stabilisation process through detailed geotechnical interventions.
Key activities included:
- Embankment Stabilisation 
- Installation of Strip Drains 
- Installation of Rock Bolts, Mesh and Mock Rock 
- Finish Retaining Wall Repairs 
- Installation of HDGAL N25 permanent rock anchors 
- Strip drainage cells and SL81 mesh 
- Installation of new reinforced retaining wall and planter boxes 
- Finished with a natural stone rock mock finish 
- Removal and reinstatement of new driveway 
 
          
          
        
      